Skip to content
Public SpendPublic SpendCapital Region
Year-over-year jumpNot reviewed

Disclosed amounts to Island Asphalt Ltd rose from $4,008,485 to $5,289,540.15

City of Victoria · fiscal 2024 → 2025 · +$1,281,055.15 (+32.0%)

1

What was observed

City of Victoria’s 2024 schedule printed $4,008,485 for this name; its 2025 schedule printed $5,289,540.15. A change of $1,281,055.15.

City of Victoria SOFI 2023, row 204City of Victoria SOFI 2024, row 222City of Victoria SOFI 2025, row 218
2

Why it’s notable

A large absolute year-over-year change in a disclosed aggregate amount.

3

How to check it

Open each schedule at the cited page and find the row. Amounts are stored as exact cents from the printed page.

4

What it may mean

Does the year-over-year change reflect a new or terminating relationship, or a re-classification or one-off, and what (if any) project or contract evidence explains it?

5

What it doesn’t prove

A year-over-year change in a disclosed aggregate amount is not evidence of a new contract, a non-competitive award, or wrongdoing. Timing and context require project, contract, or council-record evidence.

Related names

These names share this one’s stem but are printed differently. Each is a separate label, never added in, and not evidence of who received the money.

Island Asphalt CompanyCRD · OAK · SAA$8,388,672 over 2023, 2024, 2025

Share or cite

Capital Region Public Spend, “Year-over-year jump: Island Asphalt Ltd (Victoria, FY2024→2025).” Data built 2026-09-20. Candidate notice, not reviewed.

Spotted something in the source? Report a correction →